Official Karnataka RERA project record
Checked on 20 October 2026. Registration status: Approved.
- Project / phase
- After the Rain- Phase 1
- Promoter
- Total Environment Building Systems Pvt. Ltd
- Registration number
- PRM/KA/RERA/1251/309/PR/171014/000483
- Application number
- PR/KN/170731/000483
- District
- Bengaluru Urban
- Taluk
- Bengaluru North
- Project category
- Mixed Development
- Approved on
- 14/10/2017
- Proposed completion shown by RERA
- 30/04/2022
- Completion proposed at registration
- 30-06-2019
- COVID extension date
- 30-06-2020 - 30-03-2021
- Section 6 extension date
- 30-06-2019 - 30-06-2020
- Further extension date
- 30-03-2021 - 30-04-2022
Prices, unit availability, BHK, floor area, amenities and photographs have not been confirmed from a developer source for this record. A completion date in the register does not itself confirm completed construction or possession.
Search the official RERA project register
Official registration certificate